ESB Poolbeg
Project Name
ESB Poolbeg
Client:
ESB
Location:
ESB Poolbeg
Disciplines:
Demolition, Asbestos Removal, Civil Engineering and Utilities.
Duration:
30 Weeks
Sectors:
Construction
The scope of works was split into two phases, namely the Demolition Phase and the Enabling Works Phase.
Phase 1 – Demolition Works Requirements
- Preparation and implementation of Construction and Demolition Waste Management Plan.
- Ecological baseline and wildlife protection plan.
- Demolition of four existing buildings.
- Asbestos removal.
- Site Clearance.
- Site Investigation and soil classification.
- Installation of cladding to exposed face of Generator Hall following completion of demolition.
Phase 2 – Enabling Works Requirements
- Geo-scan of existing underground services.
- Slit trenching to prove position and depths of existing services.
- Installation of new fire ring main and towns watermain.
- Foul sewer diversion.
- Clean and remove existing heavy fuel oil pipe.
- Reduced level dig across site.
- CBR testing to formation level.
- Import, level and compact hardcore fill across site in preparation for follow on works.