ESB Poolbeg

Project Name

ESB Poolbeg

Client:

ESB

Location:

ESB Poolbeg

Disciplines:

Demolition, Asbestos Removal, Civil Engineering and Utilities.

Duration:

30 Weeks

Sectors:

Construction

poolbeg

The scope of works was split into two phases, namely the Demolition Phase and the Enabling Works Phase.

Phase 1 – Demolition Works Requirements

  • Preparation and implementation of Construction and Demolition Waste Management Plan.
  • Ecological baseline and wildlife protection plan.
  • Demolition of four existing buildings.
  • Asbestos removal.
  • Site Clearance.
  • Site Investigation and soil classification.
  • Installation of cladding to exposed face of Generator Hall following completion of demolition.

Phase 2 – Enabling Works Requirements

  • Geo-scan of existing underground services.
  • Slit trenching to prove position and depths of existing services.
  • Installation of new fire ring main and towns watermain.
  • Foul sewer diversion.
  • Clean and remove existing heavy fuel oil pipe.
  • Reduced level dig across site.
  • CBR testing to formation level.
  • Import, level and compact hardcore fill across site in preparation for follow on works.